Sr.No |
Towers |
Work Description |
Progress |
1 |
1,2,3,4,5,6 |
Sub Structure Work |
100% |
2 |
UGT |
Sub Structure Work |
50% |
3 |
STP |
Sub Structure Work |
50% |
4 |
ESS |
Sub Structure Work |
0% |
5 |
VCB ROOM |
Sub Structure Work |
0% |
6 |
COMMERCIAL - 1 |
Sub Structure Work |
0% |
7 |
COMMERCIAL - 2 |
Sub Structure Work |
0% |
8 |
METER ROOM |
Sub Structure Work |
0% |
9 |
ANGANWADI & COMMUNITY CENTRE |
Sub Structure Work |
0% |
10 |
1 |
Super Structure Work |
0% |
11 |
2 |
Super Structure Work |
100% |
12 |
3 |
Super Structure Work |
100% |
13 |
4 |
Super Structure Work |
100% |
14 |
5 |
Super Structure Work |
0% |
15 |
6 |
Super Structure Work |
67% |
16 |
STP |
Super Structure Work |
50% |
17 |
UGT |
Super Structure Work |
50% |
18 |
COMMERCIAL - 1 |
Super Structure Work |
0% |
19 |
COMMERCIAL - 2 |
Super Structure Work |
0% |
20 |
VCB ROOM |
Super Structure Work |
0% |
21 |
ESS |
Super Structure Work |
0% |