Sr.No |
Towers |
Work Description |
Progress |
|
1 |
1,2,3,4,5,6,7,UGT, STP, AGANWADI |
Sub Structure Work |
100% |
|
2 |
ESS |
Sub Structure Work |
0% |
|
3 |
VCB ROOM |
Sub Structure Work |
0% |
|
4 |
COMMERCIAL-1 |
Sub Structure Work |
0% |
|
5 |
COMMERCIAL-2 |
Sub Structure Work |
100% |
|
6 |
METER ROOM & VCB ROOM |
Sub Structure Work |
0% |
|
7 |
1 |
Super Structure Work |
90% |
|
8 |
2 |
Super Structure Work |
90% |
|
9 |
3 |
Super Structure Work |
90% |
|
10 |
4 |
Super Structure Work |
90% |
|
11 |
5 |
Super Structure Work |
90% |
|
12 |
6 |
Super Structure Work |
90% |
|
13 |
7 |
Super Structure Work |
90% |
|
14 |
STP |
Super Structure Work |
90% |
|
15 |
UGT |
Super Structure Work |
90% |
|
16 |
AGANWADI |
Super Structure Work |
100% |
|
17 |
COMMERCIAL-1 |
Super Structure Work |
0% |
|
18 |
COMMERCIAL-2 |
Super Structure Work |
50% |
|
19 |
VCB ROOM |
Super Structure Work |
0% |
|
20 |
ESS |
Super Structure Work |
0% |
|
21 |
2 |
Finishing work |
Tile work Door frame & Putty work (Tile work - 50%, Putty Work (1st coat) - 80% & door frame -100%) |
|
22 |
3 |
Finishing work |
Tile work ,Door frame & Putty work (Tile work - 10%, Putty Work (1st coat) - 80%, & door frame-100%) |
|
23 |
4 |
Finishing work |
Putty work & Door frame ( Putty Work (1st coat) - 80% & Door frame -100 %, ) |
|
24 |
5 |
Finishing work |
Putty work & Door frame ( Putty Work (1st coat) - 30% & Door frame -0 %, ) |