Pyramid Altia Sector-70

Pyramid Altia Sector-70

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7,UGT, STP, AGANWADI

Sub Structure Work 

100%

2

ESS

Sub Structure Work

0%

3

VCB ROOM

Sub Structure Work

0%

4

COMMERCIAL-1

Sub Structure Work

0%

5

COMMERCIAL-2

Sub Structure Work

100%

6

METER ROOM & VCB ROOM

Sub Structure Work

0%

7

1

Super Structure Work

90%

8

2

Super Structure Work 

90%

9

3

Super Structure Work 

90%

10

4

Super Structure Work 

90%

11

5

Super Structure Work 

90%

12

6

Super Structure Work 

90%

13

7

Super Structure Work 

90%

14

STP

Super Structure Work 

90%

15

UGT

Super Structure Work 

90%

16

AGANWADI

Super Structure Work 

100%

17

COMMERCIAL-1

Super Structure Work 

0%

18

COMMERCIAL-2

Super Structure Work 

50%

19

VCB ROOM

Super Structure Work 

0%

20

ESS

Super Structure Work 

0%

21

2

Finishing work 

Tile work Door frame & Putty work (Tile work - 50%, Putty Work (1st coat) - 80% & door frame -100%)

22

3

Finishing work  

Tile work ,Door frame & Putty work (Tile work - 10%, Putty Work (1st coat) - 80%, & door frame-100%)

23

4

Finishing work  

Putty work & Door frame ( Putty Work (1st coat) - 80% & Door frame -100 %, )

24

5

Finishing work 

Putty work & Door frame ( Putty Work (1st coat) - 30% & Door frame -0 %, )

 