Pyramid Altia Sector-70

Pyramid Altia Sector-70

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7,UGT, STP, AGANWADI

Sub Structure Work 

100%

2

8

Sub Structure Work

65%

3

ESS

Sub Structure Work

0%

4

VCB ROOM

Sub Structure Work

0%

5

COMMERCIAL-1

Sub Structure Work

80%

6

COMMERCIAL-2

Sub Structure Work

100%

7

METER ROOM & VCB ROOM

Sub Structure Work

0%

8

1

Super Structure Work

95%

9

2

Super Structure Work 

100%

10

3

Super Structure Work 

100%

11

4

Super Structure Work 

94%

12

5

Super Structure Work 

94%

13

6

Super Structure Work 

94%

14

7

Super Structure Work 

94%

15

STP

Super Structure Work 

90%

16

UGT

Super Structure Work 

90%

17

AGANWADI

Super Structure Work 

100%

18

COMMERCIAL-1

Super Structure Work 

0%

19

COMMERCIAL-2

Super Structure Work 

65%

20

VCB ROOM

Super Structure Work 

0%

21

ESS

Super Structure Work 

0%

22

1

Finishing work 

Putty work 25%

23

2

Finishing work  

Tile work - 93%, Putty Work (1st coat) - 90% & door frame -100%

24

3

Finishing work  

Tile work - 93%, Putty Work (1st coat) - 90% & door frame -100%

25

4

Finishing work 

Tile work start ,Putty  Work (1st coat) - 90% & Door frame -100 %, 

26

5

Finishing work 

 Tile work start,Putty Work (1st coat) - 90% & Door frame -90 %, 

 