Pyramid Altia Sector-70

Pyramid Altia Sector-70

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7,8,UGT, STP, AGANWADI, COMMERCIAL-1, COMMERCIAL-2, 

Sub Structure Work 

100%

2

METER ROOM & VCB ROOM

Sub Structure Work

10%

3

ESS

Sub Structure Work

0%

4

VCB ROOM

Sub Structure Work

0%

5

1

Super Structure Work

95%

6

2

Super Structure Work 

100%

7

3

Super Structure Work 

100%

8

4

Super Structure Work 

94%

9

5

Super Structure Work 

94%

10

6

Super Structure Work 

94%

11

7

Super Structure Work 

50%

12

STP

Super Structure Work 

90%

13

UGT

Super Structure Work 

90%

14

AGANWADI

Super Structure Work 

100%

15

COMMERCIAL-1

Super Structure Work 

10%

16

COMMERCIAL-2

Super Structure Work 

75%

17

VCB ROOM

Super Structure Work 

0%

18

ESS

Super Structure Work 

0%

19

1

Finishing work 

Putty work 75% & door fream -100%

20

2

Finishing work  

Tile work - 93%, Putty Work (1st coat) - 90% & door frame -100%

21

3

Finishing work  

Tile work - 93%, Putty Work (1st coat) - 90% & door frame -100%

22

4

Finishing work 

Tile work start ,Putty  Work (1st coat) - 90% & Door frame -100 %

23

5

Finishing work 

 Tile work start,Putty Work (1st coat) - 90% & Door frame -90 %

24

6

 

  

25

7

Finishing work 

 Putty Work (1st coat) - 90% & Door frame -90 %

 