Sr.No |
Towers |
Work Description |
Progress |
1 |
1,2,3,4,5,6,7,8,UGT, STP, AGANWADI, COMMERCIAL-1, COMMERCIAL-2, |
Sub Structure Work |
100% |
2 |
METER ROOM & VCB ROOM |
Sub Structure Work |
10% |
3 |
ESS |
Sub Structure Work |
0% |
4 |
VCB ROOM |
Sub Structure Work |
0% |
5 |
1 |
Super Structure Work |
95% |
6 |
2 |
Super Structure Work |
100% |
7 |
3 |
Super Structure Work |
100% |
8 |
4 |
Super Structure Work |
94% |
9 |
5 |
Super Structure Work |
94% |
10 |
6 |
Super Structure Work |
94% |
11 |
7 |
Super Structure Work |
50% |
12 |
STP |
Super Structure Work |
90% |
13 |
UGT |
Super Structure Work |
90% |
14 |
AGANWADI |
Super Structure Work |
100% |
15 |
COMMERCIAL-1 |
Super Structure Work |
10% |
16 |
COMMERCIAL-2 |
Super Structure Work |
75% |
17 |
VCB ROOM |
Super Structure Work |
0% |
18 |
ESS |
Super Structure Work |
0% |
19 |
1 |
Finishing work |
Putty work 75% & door fream -100% |
20 |
2 |
Finishing work |
Tile work - 93%, Putty Work (1st coat) - 90% & door frame -100% |
21 |
3 |
Finishing work |
Tile work - 93%, Putty Work (1st coat) - 90% & door frame -100% |
22 |
4 |
Finishing work |
Tile work start ,Putty Work (1st coat) - 90% & Door frame -100 % |
23 |
5 |
Finishing work |
Tile work start,Putty Work (1st coat) - 90% & Door frame -90 % |
24 |
6 |
|
|
25 |
7 |
Finishing work |
Putty Work (1st coat) - 90% & Door frame -90 % |